It was pretty much a bloodless coup, the general contractor that we're working with on this project originally wanted us to cut about $3M from our price but keep the same scope of work. We told him that we could not do that and we would withdraw our proposal. He can back to us a little later and asked for $1.3M, again we told him that we could not do that, but we would talk to our subcontractors to see what we could come up with. We finally offered him about $600K, he said he would run it by his people and tell us next week if we will get the job.
I was thinking about sub-letting the clean up to Toots. :wink: